PLAN. EXECUTE. TRIUMPH.™(512) 800-2903holly.dekle@setboundaries.com

Aerospace and defense program recovery

Scope-change claims and requests for equitable adjustment on aerospace programs

How to spot out-of-scope customer requests, document them as they happen, and substantiate scope-change claims and REAs with your own cost data.

Book a call with Hollyor call (512) 800-2903

Home / Aerospace and defense program execution / Aerospace and defense program recovery

Your customer asked for changes, your team made them, and the program absorbed the cost. Now the budget is gone, the schedule has slipped and leadership wants to know whether any of it can be recovered. On aerospace and defense programs it often can, but only if the out-of-scope work can be identified, traced to the requests that caused it and priced from real data. This guide explains how that works from the program side, and when to bring in contracts and legal staff.

This page describes program management practice, not legal advice. Contract rights and deadlines depend on the specific contract, and any request for equitable adjustment or claim should be prepared with your contracts and legal staff.

What counts as out-of-scope work?

Out-of-scope work is anything the program performs that the contract, as written and as formally changed, does not require. On highly engineered programs it rarely arrives as a single large request. It arrives in pieces: an extra analysis requested at a design review, an additional test condition at a witness event, a changed interface after a customer integration meeting, a new format for a data deliverable. Each piece looks small. Across a development program they can add up to a substantial share of the cost and many months of schedule.

The test is simple to state and harder to apply: is the work required by the statement of work, the specifications or an approved change? If not, it is new scope, and the question becomes who authorized it and who pays for it.

What is a request for equitable adjustment, and how is it different from a claim?

On US government contracts, the Changes clauses in the FAR 52.243 family allow the contracting officer to make changes within the general scope of the contract, and provide for an equitable adjustment to price and schedule when a change affects the cost or time of performance. A request for equitable adjustment, or REA, is the contractor's request for that adjustment. It is normally negotiated with the contracting officer.

A claim is more formal. Under the Disputes clause and the Contract Disputes Act, a claim is a written demand seeking, as a matter of right, payment of money or other relief, and it asks for a contracting officer's final decision. Claims above a set dollar threshold must be certified. Many disputes start as REAs and become claims only if negotiation fails. Where the government's conduct, such as technical direction, effectively requires extra work without a formal change order, the situation is often described as a constructive change.

MechanismWhere it appliesIn practice
Change order or contract amendmentCommercial purchase orders and subcontracts, and formal government changesThe cleanest route: scope and price are agreed before or alongside the work
Request for equitable adjustmentGovernment contracts, and many subcontracts that flow down similar termsA documented, priced request for adjustment, negotiated rather than litigated
ClaimGovernment contracts under the Disputes clause; commercial disputes under the contract's own termsA formal demand for a decision, with certification and legal involvement

Most aerospace suppliers are subcontractors, often to a foreign or domestic prime rather than to the government. Their rights come from their own purchase order or subcontract, which may or may not flow down the government clauses, and requests usually go to the prime rather than directly to the government. Commercial contracts use change orders and whatever change and dispute provisions the parties agreed. That is one reason contracts staff should be involved early.

How does contract type change what absorbed scope costs you?

Unfunded work hurts under every contract type, but it hurts in different ways, and that decides how fast the program has to act. Under a firm-fixed-price contract the loss lands directly on margin. Under a cost-reimbursement contract the customer may keep paying for a while, which hides the problem until the funding runs out and the required work is not finished.

Contract typeChanges clauseWhat absorbed scope doesWhat to watch
Firm-fixed-priceFAR 52.243-1Comes straight out of margin, with no automatic reliefThe 30-day window to assert an adjustment, and any notification clause
Cost-reimbursementFAR 52.243-2Uses up funded value, so the program reaches its limit with required work left to doLimitation of Cost or Limitation of Funds notices, generally at 75 percent
Time-and-materialsFAR 52.243-3Spends hours against the ceiling price on tasks nobody pricedRemaining ceiling, and who approved work outside the task
Commercial purchase orderIts own termsUsually comes out of margin, and can set a precedent for the next requestChange and notice terms, and any rule that changes must be in writing

The cost-reimbursement row is the one that surprises people. Under the Limitation of Cost and Limitation of Funds clauses, FAR 52.232-20 and 52.232-22, the contractor gives notice when it expects to reach 75 percent of the estimated cost or allotted funds within the next 60 days, unless the contract sets a different percentage. If extra requests have been eating that money, the notice arrives early and the customer asks why. It is much better to have that conversation while the work can still be reprioritized.

How do you recognize out-of-scope requests as they happen?

The best time to catch new scope is the moment it is requested. Common signals include:

None of these is wrong for the customer to ask. The problem is accepting them silently. A signed project charter and a controlled path for technical requests give the team a way to say "we will assess that and come back to you" without refusing to help.

Who on the customer side can actually change your contract?

Usually far fewer people than the team assumes. On US government contracts, only contracting officers acting within their authority can modify a contract, as FAR 43.102 states. Engineers, technical representatives and most program office staff cannot, even when they are senior and the program depends on their goodwill. The Department of Defense makes the same point in its clause on contracting officer's representatives, DFARS 252.201-7000, which says a representative is not authorized to make commitments or changes that affect price, quality, quantity or delivery.

This matters because direction from someone without authority can leave the contractor doing the work at its own risk, and extra work done with no direction at all can look voluntary. Whether a given instruction amounts to a constructive change depends on the facts, including what the authorized people knew and whether they accepted it. The program should not have to guess. Where FAR 52.243-7 is in the contract, it sets the notification route. Elsewhere, name the authorized people on both sides in the project charter, so the team knows which requests are direction and which are conversation.

How should changes be documented at the time?

Contemporaneous records are worth far more than reconstructions. For each request, the program should record the date, who asked, exactly what was asked, the requirement it relates to or the absence of one, who on the program accepted it, what configuration items it affects and a first estimate of the cost and schedule impact. Meeting minutes, customer emails and review comments should be filed where they can be found later.

Timing also matters. Many contracts require prompt notice when the contractor believes a change has occurred. For example, the standard fixed-price Changes clause asks the contractor to assert its right to an adjustment within 30 days of receiving a written change order, and some contracts add a notification-of-changes clause for constructive changes. Read your own contract, because the deadlines that apply to you are the ones in it.

How do you trace configuration changes back to requests?

On a development program that has gone through several design iterations, the most reliable method is to work configuration by configuration. Review each iteration of the product, identify every change between one configuration and the next, and trace each change to its cause: a contract requirement, an approved change, a correction of the contractor's own error, or an informal customer request. Only the last category supports an adjustment, and being honest about the others is what makes the remaining items credible.

This is where a requirements-to-work assessment and good configuration management pay off. The compliance matrix shows which features are required. The configuration records show when each change was made. Together with the meeting records, they connect each change to the request that caused it.

How do you quantify the cost and schedule impact?

From the company's own financial data, not estimates made after the fact. Labor charged to the affected work, material and tooling, test facility time, rework and scrap, and supplier charges can usually be identified from the accounting and time-charging systems. Schedule impact should come from the program schedule: which activities the change added or extended, and whether they sat on the critical path.

Credibility depends on separation. Costs caused by the contractor's own problems, such as a supplier defect or an internal redesign, must be excluded. An adjustment request that includes everything that went wrong on the program will be discounted as a whole. One that isolates the changed work, shows the trace from request to configuration change to cost, and explains its method clearly is much harder to dismiss. Government contractors should expect the numbers to be audited, and should prepare them to that standard.

What rules apply once a request is submitted?

A priced request is a formal statement to the customer, and on government work several rules attach to it. Which ones apply depends on the customer, the size of the request and the clauses in the contract, so treat this as a list to check with your contracts staff.

The person who signs needs to know how the numbers were built. A knowingly overstated submission can create liability under the False Claims Act and the Contract Disputes Act, on top of damaging the program's credibility with the customer. Clause text and numbering also change over time, and the FAR has been going through a major rewrite, so check every citation here against the clauses and dates in your own contract.

How do you get new scope funded instead of absorbed?

The best outcome is to never need a claim. When a new request is identified before the work is done, the program can price it and give the customer a choice: fund the change, defer it, or proceed without it. Customers often fund changes they genuinely need when the request is presented promptly, clearly and with a sensible price. What they resist is a large, surprising bill for work they believed was included.

Should the team keep working while a change is disputed?

On US government contracts with the standard clauses, generally yes. FAR 52.243-1 says that failure to agree on an adjustment is a dispute, and that it does not excuse the contractor from proceeding with the contract as changed. The Disputes clause, FAR 52.233-1, also requires diligent performance while a dispute is resolved. Stopping work can turn an argument about price into a much more serious argument about default.

That duty applies to a change directed by someone with authority. It does not mean every informal request from a customer engineer has to be done. Informal requests go through the controlled path, and the team keeps executing the plan while they are assessed. Commercial contracts differ, so a supplier under a purchase order should confirm what its own terms require before slowing or stopping anything.

REA, claim or negotiated settlement: which route fits?

Each route trades speed and relationship against formality and leverage over the outcome. Leadership should choose it deliberately, because the route taken affects the customer relationship on the rest of the program.

QuestionREAContract Disputes Act claimCommercial settlement
Who decides?The parties, by negotiation with the contracting officerThe contracting officer, by final decision, with appeal rights after thatThe parties, then the dispute process in the contract
Certification?Required for DoD requests above the simplified acquisition thresholdRequired above $100,000Only if the contract requires it
Interest?Generally not running while it is only a requestRuns from the date the contracting officer receives the claimSet by the contract and governing law
Time limits?Contract notice periods, and the claim deadline if it may become a claimSix years from accrual to submit; set periods to appeal a final decisionSet by the contract and governing law
Effect on the relationship?Usually manageable if presented early and factuallyMore adversarial, with lawyers on both sidesDepends on the customer, and often on future work

The Contract Disputes Act sets a clear clock. A contracting officer must decide a claim of $100,000 or less within 60 days if the contractor asks, and for a larger claim must decide or give a firm date within 60 days. After a final decision, the contractor generally has 90 days to appeal to a board of contract appeals or 12 months to file in the Court of Federal Claims. Miss those periods and the decision can become final, which is why counsel should be in the room before a claim goes in.

Money is only part of the choice. The size of the request, the work remaining, any follow-on production and the customer's own pressures all belong in the decision. Our part is to show leadership what each path costs in schedule, money and risk, so the choice is made with the facts on the table. To talk through a program in this position, book a call.

What changes when your customer is a prime or a foreign OEM?

A subcontractor usually cannot take a government claim directly to the government. It relies on the prime to sponsor the request. Under the Severin doctrine, a prime can generally pass a claim through only if it remains liable to the subcontractor, so a broad release in the subcontract can quietly end the route. Primes and subcontractors often sign a liquidating agreement to deal with this. The prime also has to be willing to put its name on the submission, and its own notice period to the government keeps running, so a supplier that waits may leave the prime with no time to act.

On a commercial sale of goods under US state law, Section 2-209 of the Uniform Commercial Code matters. A modification can be binding without new consideration, and a clause requiring written changes is generally enforced, but conduct can amount to a waiver of that clause. A team that has been quietly accepting informal changes for a year may have weakened its own position.

A foreign customer adds further questions: which country's law governs, where disputes are heard, and whether the contract language controls over any translation. Substantiating data can also be export controlled. Drawings and technical records assembled for a submission may need review under ITAR or EAR before they go to a foreign customer, even when that customer has seen similar data before.

Where do contracts and legal staff come in?

Early, and throughout. The program team owns the facts: what was requested, what was done, what it cost and how it affected the schedule. Contracts staff own the contract position: which clauses apply, what notice was required, and how the request should be framed. Legal counsel should be involved before anything is presented as a claim, and whenever deadlines, certification or disputes are in question. The strongest submissions come from all three working together, with the program providing evidence that stands on its own.

How Set Boundaries helps

Set Boundaries helps programs stop absorbing uncontrolled scope and recover what they can. We set up the controlled path for customer requests, build the compliance matrix and configuration trace, and work with your finance, contracts and legal staff to quantify the impact from your own data. We do not provide legal advice, and we do not promise outcomes on claims. We make sure the program side of the case is factual, traceable and complete. If your program has been absorbing customer requests, schedule a call.

Related guides

References

Questions

Common questions

What is a request for equitable adjustment?

A request for equitable adjustment, or REA, is a contractor's documented request to adjust contract price, schedule or both because the government changed the work or otherwise affected the cost or time of performance. It is normally negotiated with the contracting officer rather than litigated. A strong REA identifies the change, shows how it was directed, traces it to the affected work and prices the impact from the contractor's own records.

What is the difference between an REA and a claim?

An REA is a request that the parties negotiate. A claim, under the Disputes clause and the Contract Disputes Act, is a formal written demand for payment or other relief as a matter of right, seeking a contracting officer's final decision, and claims above a set threshold must be certified. Many disputes begin as REAs and become claims only if negotiation fails. Contracts and legal staff should be involved in both.

What is a constructive change?

A constructive change occurs when the customer's conduct effectively requires work beyond the contract without issuing a formal change order. Common examples are technical direction from customer engineers, rejection of compliant deliverables, or demands for tests the contract does not require. The contractor may be entitled to an adjustment, but notice requirements and proof of who directed the work matter a great deal, which is why contemporaneous records are so important.

How quickly do you have to notify the customer of a change?

It depends on the contract. The standard fixed-price Changes clause asks the contractor to assert its right to an adjustment within 30 days of receiving a written change order, and some contracts add notification requirements for constructive changes. Commercial purchase orders and subcontracts set their own terms. The practical rule is to raise new scope as soon as it is identified and have contracts staff confirm the deadlines in your contract.

Can a subcontractor submit an REA to the government?

Usually not directly. A subcontractor normally has no contract with the government, so it raises the matter with the prime contractor under its own subcontract terms. The prime may pass a subcontractor's request through to the government where the change originated there. Many aerospace suppliers work under commercial purchase orders with domestic or foreign primes, in which case the purchase order's change and dispute provisions govern.

What evidence supports a scope-change claim?

Contemporaneous records of each request, including who asked, when and what, a compliance matrix showing the work was not required, configuration records tracing each design change to its cause, and cost and schedule data from the company's own accounting and scheduling systems. Costs caused by the contractor's own problems should be excluded. A clear, conservative submission with a transparent method is far more persuasive than a large total with weak support.

Have a question that is not here? Ask Holly on a short call

Talk to Holly

Program slipping, or the customer losing patience?

Tell Holly what is happening. She will tell you where she would look first and whether Set Boundaries can help, in a short call.

  • You speak with Holly directly, not a salesperson.
  • Bring the real problem: the schedule, the customer, the scope or the closeout.
  • You leave knowing whether we can help and what the first step would be. No obligation.

Book a call with Hollyor call (512) 800-2903

Not ready to talk yet? Take the three-minute program health check.

Holly Dekle, PMP
Holly Dekle, PMPFounder, Set Boundaries. Engineer, more than two decades of aerospace, defense and maritime programs.
Talk to Holly about your programBook a call